Subsequent Purchaser of Water/Mold Damaged House Time-Barred in Suit Against Builder
April 26, 2003
DOCUMENTS
- Opinion
SAINT PAUL, Minn. - On April 9, the Minnesota Court of Appeals affirmed a district court's ruling that the subsequent purchaser of a water/mold damaged house is barred by the statute of limitations from filing suit against the original builder and construction contractors. Dean P. Vlahos, et al., Appellants, v. R&I Construction of Bloomington, Inc., f/k/a Robert Waade & Associates, Inc., et al., Respondents, John Doe, et al., Defendants; and R&I Construction of Bloomington, Inc., f/k/a Robert Waade & Associates, Inc., et al., Third Party Plaintiffs, Respondents, v. Quality Insulation, Inc., Third Party Defendant, Respondent, et al., No. C7-02-1428 (Minn. …